November marks two years since the launch of Rail Baltica’s Riga Central Hub construction, which was started in 2020. Until now, 68% of the piles of the southern side of the track are built, 45,000 m3 of railway embankment excavated and a 230 meters long railway embankment retaining wall is built, as well as 43 km of new […]
Riga Central Hub
Year
Time capsule embedded into foundations of the Rail Baltica Central Hub in Riga marking the start of next construction phase
To leave a message for the future generations, on 20 July 2022, at the construction site of the future Rail Baltica Central Hub in Riga, the parties involved in the project solemnly embedded a time capsule in the foundations of the new station building grounds. Preparation of the time capsule started already last September, […]