Two years for the construction of Rail Baltica Riga Central Hub: 100 km of railway signaling cables and 1700 piles built

November marks two years since the launch of Rail Baltica’s Riga Central Hub construction, which was started in 2020. Until now, 68% of the piles of the southern side of the track are built, 45,000 m3 of railway embankment excavated and a 230 meters long railway embankment retaining wall is built, as well as 43 km of new […]

Time capsule embedded into foundations of the Rail Baltica Central Hub in Riga marking the start of next construction phase

  To leave a message for the future generations, on 20 July 2022, at the construction site of the future Rail Baltica Central Hub in Riga, the parties involved in the project solemnly embedded a time capsule in the foundations of the new station building grounds. Preparation of the time capsule started already last September, […]