Procurement plan 2026
Below is a preliminary list of Rail Baltica tenders planned for 2026 across the Baltic states. Please note that this draft is subject to change. For information on the relevant contracting authorities, refer to the Rail Baltica governance structure.
| Procurement title | Category | Indicative start date | Contracting authority | Status |
|---|---|---|---|---|
| Rail Baltica railway line section Kaunas (Palemonas) – Šveicarija 0.5 – 9.0 km (8.5 km) expertise services for the detailed technical design part (constructions) | Services | 2026 Q2 | LTG Infra | To be announced |
| Technical Supervision of Construction Works and Engineering Services | Services | LTG Infra | Announced | |
| Construction Surveys (Engineering Services) – Technical supervision | Services | LTG Infra | Announced | |
| Expert evaluation services for the technical, detailed design, and working drawings of the Rail Baltica project | Services | LTG Infra | Announced | |
| RB line Kaunas-Panevėžys-LT/LV border new railway embankment construction in section Berčiūnai-Joniškėlis 102.43-114.71 km (12.28 km) expertise services for the detailed technical design part (constructions) | Services | 2026 Q3 | LTG Infra | To be announced |
| RB line Kaunas-Panevėžys-LT/LV border new railway embankment construction in section Ramygala-Berčiūnai 78 – 102.43 km (24.43 km) expertise services for the detailed technical design part (constructions) | Services | 2026 Q3 | LTG Infra | To be announced |
| Construction of a new railway embankment for RB line Kaunas-Panevėžys-LT/LV border on the Berčiūnai Joniškėlis section 102.43 – 114,71 km (12.28 km) laboratory testing and research services | Services | 2026 Q2 | LTG Infra | To be announced |
| Construction of a new railway embankment for RB line Kaunas-Panevėžys-LT/LV border on the Berčiūnai Joniškėlis section 102.43 – 114,71 km (12.28 km) laboratory testing and research services | Services | 2026 Q3 | LTG Infra | To be announced |
| Construction of a new railway embankment for RB line Kaunas-Panevėžys-LT/LV border on the Ramygala – Berčiūnai section 78 – 102.43 km (24.43 km) laboratory testing and research services | Services | 2026 Q3 | LTG Infra | To be announced |
| Construction of the railway superstructure for RB section Šveicarija-Žeimiai laboratory testing and research services | Services | 2026 Q2 | LTG Infra | To be announced |
| Laboratory testing and reserch services (Šveicarija-Žeimiai, Neris Bridge, Žeimiai-Šėta) | N/A | 2026 Q2 | LTG Infra | To be announced |
| Construction of a new railway embankment for Rail Baltica on the Šėta–Ramygala section 65.9–78 km (12.1 km) laboratory testing and research services | Services | 2026 Q2 | LTG Infra | To be announced |
| Construction of a new railway embankment for Rail Baltica on the Kaunas (Palemonas) – Šveicarija 0.5 – 9.0 km (8.5 km) laboratory testing and research services | Services | 2026 Q2 | LTG Infra | To be announced |
| Construction of a new railway embankment for Rail Baltica on the Kaunas (Palemonas) – Šveicarija 9.0 – 19.4 km (10.4 km) laboratory testing and research services | Services | 2026 Q2 | LTG Infra | To be announced |
| Rail Baltica laboratory testing and reserch services (RB) (Qualification Asessment System) | Services | 2026 Q2 | LTG Infra | To be announced |
| Construction works for the installation of the superstructure of the Rail Baltica railway line (RB) (Qualification Assesment System) | Works | 2026 Q2 | LTG Infra | To be announced |